After the charging pile is connected to HEMS, what is the execution priority of the system's internal scheduling when the user activates both "Charging Pile Usage Time" and "TOU Mode" at the same time?

After the charging pile is connected to HEMS, what is the execution priority of the system's internal scheduling when the user activates both "Charging Pile Usage Time" and "TOU Mode" at the same time?

​The internal dispatch priority is fixed as: Charger Use Time > Solar Surplus > Low Tariff.
​The system only permits charging during the designated charger use time window, prioritizing surplus solar power first and low-tariff grid power second. If neither condition is met, the charger will not initiate charging.